How to change the Page title for a network in a ProWORX 32 project

Goals and Symptoms

The goal is to provide an example on how to change the 'Page Title' for a network in a 'ProWORX 32' project.

Causes and Fixes


The following is an example on editng the 'Page Title' for a network using the
'Page Down'key to goto the next network.

  • Create a new project.
  • Added 6 netowrks to the new project.
  • Click on Network 1 in the Network Navigator
  • Click on the 'Page Title' textbox in the Documentation window
  • Change the 'Page Title' to the first network,
  • Click on the logic (this needs to be done in order to put the focus back
onto the logic) and hit the page down button to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the second network.
  • Click on the logic (this needs to be done in order to put the focus back
onto the logic) and hit the page down button to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the third network.
  • Click on the logic (this needs to be done in order to put the focus back
onto the logic) and hit the page down button to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the fourth network.
  • Click on the logic (this needs to be done in order to put the focus back
onto the logic) and hit the page down button to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the fifth network,
  • Click on the logic (this needs to be done in order to put the focus back
onto the logic) and hit the page down button to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the sixth network.
  • Click on the logic (this needs to be done in order to put the focus back
onto the logic) and hit the page down button to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)



The following is an example on editng the 'Page Title' for a network using the
mouse click in 'Network Navigator' to goto the next network.
  • Create a new project.
  • Added 6 netowrks to the new project.
  • Click on Network 1 in the Network Navigator
  • Click on the 'Page Title' textbox in the Documentation window
  • Change the 'Page Title' to the first network,
  • Click on the next network in the 'Network Navigator to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the second network.
  • Click on the next network in the 'Network Navigator to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the third network.
  • Click on the next network in the 'Network Navigator to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the fourth network.
  • Click on the next network in the 'Network Navigator to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the fifth network,
  • Click on the next network in the 'Network Navigator to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)
  • Click on the 'Page Title' textbox in the Documentation window.
  • Change the title to the sixth network.
  • Click on the next network in the 'Network Navigator to goto the next network.
(at this point, the performance bar will appear to indicate that the changes
have been accepted.)

Note: Even though the changes have been accepted in the project, they have not been saved to
the database. A save function must be performed in order to save the changes to the
project database.
Was this helpful?
What can we do to improve the information ?