In Unity Hot Standby, is it possible to copy the project in the Primary to the Standby CPU without using the keypad?

Yes.Unity will allow you to copy the project running in the Primary CPU to the Standby CPU by using bit 5 (binary weight 32) of %SW60. Log into the Primary CPU and open an Animation Table. Turn bit 5 of %SW60 "on". The bit will automatically turn off after the transfer is complete.